Your Clean Energy Plant Project
These are the steps towards your clean energy plant:
Pos
Task
Time
(months)
1.
Feasibility Study is always the initial task towards your clean energy plant. The feasibility study is performed by BNL Clean Energy experts and includes site selection, asessment and verfication of feedstock, capacities, product handling, logistics.

The feasibility study will present the information required for the plant offer and our guarantees. Contact your local BNL Clean Energy representativ to have your feasibility study made.

3-4
2.
Business Plan is the next task, outlining the commercial structure and planning for your clean energy plant. The business plant together with the feasibility study are used for financing, permitting and planning. The business plan is performed by the project principal. If required BNL Clean Energy can act as an advisor to the project principal.
3-4
3.
Financing is generally based on the data from the feasibility study and the business plan. For clean energy plants there are many options for funding, trading carbon credits and green funds, grants and loans available.
1-2
4.
Purchasing includes signing the contract for your clean energy plants, plant maintenance and the full service contracts. Staff training and other services must also be purchased.
1-2
5.
Permitting is started as soon as the project principal has signed the purchase contract and is based on the investigations made for licensing during the feasibility study.
6-12
6.
Delivery of your turn-key clean energy plant follows as soon as positive statements regarding permitting has beeen received.

Delivery of the clean energy plant is usually scheduled to be 12-18 months from the date of signing the purchase agreement.

12-18
7.
Commissioning includes clean energy plants, service and maintenance agreement, staff training, logistic etc.plants the organisation and staff required to manage and run the etire project. This should also include any external specilaists or contractors required to support.
2-3
Total estimated delivery time for your clean energy plant:
18-24